Waste water treatment Plant

Eastern Wastewater Treatment Plant

WASA Faisalabad is taking a significant step toward improving water quality and public health with the construction of the Eastern Wastewater Treatment Plant (WWTP). This ambitious project aims to manage wastewater sustainably, protect natural resources, and support Faisalabad’s urban growth. Here’s an overview of what the Eastern WWTP means for the community, the environment, and the future of water management in Faisalabad.

Project Overview

The Eastern WWTP, designed to treat up to 44 million gallons per day (MGD) of wastewater, is a key initiative led by WASA Faisalabad. Now in Phase I, this plant will treat wastewater before it enters natural water bodies, helping to prevent pollution, improve water quality, and create a healthier environment for Faisalabad’s residents.

Key Highlights:

Why Faisalabad Needs an Advanced Wastewater Treatment Plant

Faisalabad’s rapid growth and industrial activity have resulted in increased wastewater production. Without effective treatment, this wastewater can harm rivers, ecosystems, and public health. WASA Faisalabad’s Eastern WWTP is a critical step in addressing these challenges by aligning the city’s water management practices with modern environmental standards.

Key Benefits:

The Project in Detail

The Eastern WWTP is a sophisticated system, designed to collect, treat, and safely discharge wastewater. Here’s an outline of how the project works:

Positive Impacts on the Community and Environment

WASA Faisalabad’s Eastern WWTP project promises multiple long-term benefits for the city and its residents:

Conclusion

With the Eastern Wastewater Treatment Plant, WASA Faisalabad is leading the way toward a healthier and more sustainable future. By treating wastewater efficiently and responsibly, the agency is protecting the environment and ensuring a better quality of life for Faisalabad’s residents. This project is not only a solution to today’s water quality challenges but also an investment in Faisalabad’s sustainable growth and environmental resilience.

Construction of Eastern Wastewater Treatment Plant (33 MGD) of Faisalabad City, (Phase I)

Background

Location Chak No. : 244/RB, Faisalabad 
Sponsoring Agency DSIF :  Denmark (Tied Loan + 35 % Grant) & Government of Punjab
Executing Agency : WASA, Faisalabad
Gestation Period Original : Approved: 48 Months
Proposed: 122 Months
Approved Cost
(27-07-2020) : PKR 19,071.222 Million
L.C: PKR 1833.043 Million
F.C: PKR 17,238.179 Million (Euro 100 Million)
Revised Cost
(Proposed ) : 
Total PKR 56,036.79 Million
L.C: PKR 2,815.53 Million
F.C PKR 53,221.26 Million (Euro 178.00 Million)
Expenditure till date L.C : PKR 123.26 Million, F.C: Nil

Scope of Project

Mode

Design Build and Operate (DBO) (3 Years Construction + 3 Years Operation)

Outcome of the Project

Status